Monday, April 7, 2008

CONSTRUCTION SCHEDULE/GUESS-TIMATE

Spoke to our Site Supervisor to day who informed me that he will no longer be dealing with our job as he has been kicked upstairs but he gave me the new SS name and number. He also gave us a new construction schedule which is as follows:-
  1. Bricking 18th April
  2. Roof 25th April
  3. Plaster 9th May
  4. Tiling 23rd May
  5. Painting 30th May
  6. Fit out 27th June
  7. Handover 8th August

Lets hope this timeline is accurate because if it is it means we will be able to watch the Olympics live on the Big Screen! You Beauty!!!