Friday, April 18, 2008

BRICKWORK - UPDATE


East side of house looking towards en suite window still to be bricked

Rear of house bedrooms 3 & 4 and Home theatre

West side of house looking towards the street

Dining area

Dining area again

Living area

Kitchen

Butlers pantry & rear garage doorway

Garage

Aam was in Cranbourne tonight after work looking at rental properties and of course she had to go and check on progress at the house. It appears that the brickies still have some way to go yet as they have still to start the front of the house.

According to the construction schedule all brickwork should have been completed by today so that makes us about 1 week behind now. Good weather forecast for next week which means we should see plenty of progress.