After waiting for over a month since the slab was poured and after numerous phone calls and emails to the builder work has finally commenced on the frame. During this waiting period we have been given a couple of excuses as to why there has been no action, these being:-
- Delays in getting the prefabricated trusses
- Colour selections not being finalised
We find both of these reasons pretty poor as we gave our colour selections back in December and the frame usually supports the trusses so why that at least was not started who knows. Maybe they were going to use skyhooks!! LOL!
Our site Supervisor has given us a tentative construction schedule.
14th March Frame complete
21st March Fascia boards, Gutters and roof
We will believe it when we see it.
We have decided not to get our down lights fitted by the builder which means they are now going to charge us a Post Contract Variation of $750! Outrageous. However we will still save over $1000 and get extra down lights.
We have also paid deposits on our A/C, Carpets etc.