Shower base sealed & graded
Shower base water proofed
Tiles laid
Laundry floor tiled
Ducted vacuum
Benchtop support
Well here we are nearly 3 weeks since the last update and frankly not a hell of a lot has been done since then. Here is a list:-
1. Shower bases graded and sealed
1. Shower bases graded and sealed
2. Waterproofing to wet areas
3. Tiles laid to Laundry, Bathroom & En suite floors (not yet grouted)
4. Part of ducted vacuum system installed
5. Faulty benchtop support replaced
Last Friday I met with the SS on site to discuss progress or lack thereof and to confirm whether 25 October would still be the date of final inspection. Surprise surprise we are now looking at the first or second week of November for this and all being well settlement late November!! Bloody hell this is slow and frustrating.