How does this bloody thing open?

Aam looking in control

Canopy with plaster work nearly completed

Typical example of cornice

cornices in en suite done

Master bedroom cornices done

WIR


Dining area



Entrance to lounge

Lounge
The Boss visited site today to check on progress and found that most of the cornices have been fitted. According to the SS plastering was to be finished by Friday this week and doors and architraves should be delivered on site tomorrow. Expecting fit out of kitchen etc to commence next week.